Step 5:  Pour Foundation.

September 29

This waiting is making us NUTS!  They were supposed to be back a week after the footings were poured, but, no... why should we be so lucky.
But at last, they showed up with a vengeance. Three crews!  22 people, 6 trucks, a whole lot of cars.  They put up the forms.  The inspector dropped by and signed off and then cement trucks - six of them came up (right behind the cement pumper and they started pouring.  
By 6 p.m. we had a foundation for the house.

October 9
The garage was poured today.  They started on Friday, but quit because they thought it would rain. It did rain in parts of the valley, just not at the property.  So they came back and finished on Monday.  

Glenn waterproofed the house foundation on October 17 and the garage on October 28.
Now it's starting to look like a house!